Thursday, August 8, 2013

'Critical phase' for Iter fusion dream

'Critical phase' for Iter fusion dream

Tokamak construction   IterThe foundations for Iter's tokamak - which will contain the hot plasma - have been laid
The world's largest bid to harness the power of fusion has entered a "critical" phase in southern France.
The Iter project at Cadarache in Provence is receiving the first of about one million components for its experimental reactor.
Dogged by massive cost rises and long delays, building work is currently nearly two years behind schedule.
The construction of the key building has even been altered to allow for the late delivery of key components.
"We're not hiding anything - it's incredibly frustrating," David Campbell, a deputy director, told BBC News.
"Now we're doing everything we can to recover as much time as possible.
"The project is inspiring enough to give you the energy to carry on - we'd all like to see fusion energy as soon as possible."

Fusion facts

Jet tokamak
  • Fusion is the process that powers the stars including the Sun
  • One litre of water contains enough deuterium, when fused with tritium, to produce the equivalent energy of 500 litres of petrol
  • A 1,500MW fusion power station would consume about 600g of tritium and 400g of deuterium a day
  • The first large-scale use of fusion was by the US military with the detonation of Ivy Mike, a hydrogen bomb, on 1 November 1952.
  • Iter's design involves a tokamak, the Russian word for a ring-shaped magnetic chamber
  • The magnetic field is designed to contain 100 million degree plasma, the temperature required for the fusion process
  • The US, while supporting Iter as a partner, is also funding the National Ignition Facility, which uses lasers to heat and compress hydrogen to the point of fusion
  • South Korea, another Iter partner, is investing $941m in a fusion technology demonstrator, K-DEMO, which could be the first to generate Grid power
  • Critics object to further research into nuclear power and question the likely costs of commercial operations
After initial design problems and early difficulties co-ordinating this unique international project, there is now more confidence about the timetable.
Since the 1950s, fusion has offered the dream of almost limitless energy - copying the fireball process that powers the Sun - fuelled by two readily available forms of hydrogen.
The attraction is a combination of cheap fuel, relatively little radioactive waste and no emissions of greenhouse gases.
But the technical challenges of not only handling such an extreme process but also designing ways of extracting energy from it have always been immense.
In fact, fusion has long been described as so difficult to achieve that it's always been touted as being "30 years away".
Now the Iter reactor will put that to the test. Known as a "tokamak", it is based on the design of Jet, a European pilot project at Culham in Oxfordshire.
It will involve creating a plasma of superheated gas reaching temperatures of more than 200 million C - conditions hot enough to force deuterium and tritium atoms to fuse together and release energy.
The whole process will take place inside a giant magnetic field in the shape of a ring - the only way such extreme heat can be contained.
The plant at JET has managed to achieve fusion reactions in very short bursts but required the use of more power than it was able to produce.
The reactor at Iter is on a much larger scale and is designed to generate 10 times more power - 500 MW - than it will consume.
France's fusion reactor would work like the sun
Iter brings together the scientific and political weight of governments representing more than half the world's population - including the European Union, which is supporting nearly half the cost of the project, together with China, India, Japan, Russia, South Korea and the United States.
Contributions are mainly "in kind" rather than in cash with, for example, the EU providing all the buildings and infrastructure - which is why an exact figure for cost is not available. The rough overall budget is described as £13bn or 15bn euros.
But the novel structure of Iter has itself caused friction and delays, especially in the early days.
Each partner first had to set up a domestic "agency" to handle the procurement of components within each member country, and there have been complications with import duties and taxes.
Further delay crept in with disputes over access to manufacturing sites in partner countries. Because each part has to meet extremely high specifications, inspectors from Iter and the French nuclear authorities have had to negotiate visits to companies not used to outside scrutiny.
The result is that although a timeline for the delivery of the key elements has been agreed, there's a recognition that more hold-ups are almost inevitable.
The main building to house the tokamak has been adjusted to leave gaps in its sides so that late components can be added without too much disruption.
The route from the ports to the construction site has had to be improved to handle huge components weighing up to 600 tonnes, but this work too has been slower than hoped. A trial convoy originally scheduled for last January has slipped to this coming September.
IterPreparation work at the Iter site in Cadarache began in 2007. Some 90 hectares has been cleared and levelled for scientific buildings and facilities, leaving the other half of the site in its original wooded state
1/5
Under an initial plan, it had once been hoped to achieve the first plasma by the middle of the last decade.
Then, after a redesign, a new deadline of November 2020 was set but that too is now in doubt. Managers say they are doubling shifts to accelerate the pace of construction. It's thought that even a start date during 2021 may be challenging.
The man in charge of coordinating the assembly of the reactor is Ken Blackler.
"We've now started for real," he told me. "Industrial manufacturing is now under way so the timescale is much more certain - many technical challenges have been solved.
"But Iter is incredibly complicated. The pieces are being made all around the world - they'll be shipped here.
"We'll have to orchestrate their arrival and build them step by step so everything will have to arrive in the right order - it's really a critical point."
Command and control
While one major concern is the arrival sequence of major components, another is that the components themselves are of sufficiently high quality for the system to function.
The 28 magnets that will create the field containing the plasma have to be machined to a very demanding level of accuracy. And each part must be structurally sound and then welded together to ensure a totally tight vacuum - without which the plasma cannot be maintained. A single fault or weakness could jeopardise the entire project.
Assuming Iter does succeed in proving that fusion can produce more power than it consumes, the next step will be for the international partners to follow up with a technology demonstration project - a test-bed for the components and systems needed for a commercial reactor.
Ironically, the greater the progress, the more apparent becomes the scale of the challenge of devising a fusion reactor that will be ready for market.
At a conference in Belgium last September, I asked a panel of experts when the first commercially-available fusion reactor might generate power for the grid.
A few said that could happen within 40 years but most said it would take another 50 or even 60 years. The fusion dream has never been worked on so vigorously. But turning it into reality is much more than 30 years away.

More Science & Environment stories

RSS

BBC Future

Braille screen

Bumpy touchscreen changes lives

Raising phone design to another dimension Read more...

Programmes

  • MeatHARDtalkWatch

    How meat could be grown in our kitchens - but we will need to plan our meals two months ahead

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.